Oracle FAQ | Your Portal to the Oracle Knowledge Grid |
![]() |
![]() |
Home -> Community -> Usenet -> c.d.o.server -> Re: Upgrade/migration time estimates
If everything goes smoothly,datafile conversion takes only 2 hours for 20Gb
database. So the approximate estimated time would be 8 hours for all operation.
Mohamed
Jonathan Gauthier wrote:
> I'm preparing an upgrade from 7.3.3.5 to 7.3.4 followed later by a migration
> from 7.3.4 to 8.1.5.
> I have to do it in two steps because of application compliance issues.
> I'd like to know what is the approximate time these two operations will take
> for a 20gig database.
> I only need estimations for the actual operation not counting backups and
> preparation. Just the time it takes for Oracle to convert the datafiles to
> the new version.
>
> The computer is a Sun ultrasparc 2 with 2 CPUs(300mhz) and 1 gig of RAM.
> Datafiles are spread on several disks.
>
> Please answer with a copy to my email address if possible.
>
> --
> ---
Received on Wed Jan 26 2000 - 13:51:40 CST
![]() |
![]() |