Good morning,
Jason was quicker :) He's absolutely right, as far as I remember back Clusterware was rolling. I haven't used CRS 10.1 though.
Here's an example for 10.2.0.1->10.2.0.5: http://martincarstenbach.wordpress.com/2010/05/26/patching-crs-to-10-2-0-5/
And another one for 10.2 to 11.2:
http://martincarstenbach.wordpress.com/2010/01/21/upgrade-clusterware-10-2-to-11-2/
As a side note, you can defer the ASM upgrade during the 11.2 migration, but I wouldn't recomend it.
No need to do primary and standby database(s) at the same time, but there is the implication that your environment is (slightly) out of sync which is known to irritate managers for a week.
Regards,
Martin Bach
http://martincarstenbach.wordpress.com/
uk.linkedin.com/in/martincarstenbach
> Hi,
>
> It is not to true to say you cannot do a rolling clusterware upgrade.
>
> This is very much possible. Here is a link to performing a rolling
> clusterware upgrade from 10.2.0.3 -> 10.2.0.4:
>
> https://jarneil.wordpress.com/2008/06/23/rolling-oracle-clusterware-upgrade-to-10204/
>
> You can also see from there how to do a 10.2.0.3 to 11.1.0.6 clusterware
> upgrade in a rolling fashion.
>
> Where you get the problem is that ASM is not rolling until 11.1, however
> this should not prevent clusterware itself being upgraded in a rolling
> fashion at 10gR2.
>
> cheers,
>
> jason.
>
> --
> http://blog.jarneil.co.uk
>
>
> On 2 Feb 2011, at 21:42, Upendra N wrote:
>
>> I don't believe you can do a rolling upgrade of clusterware until
>> 11.2.0.1.
>> http://download.oracle.com/docs/cd/E11882_01/server.112/e17128/chapter1.htm#NEWFTCH1
>>
>> -Upendra
>>
>>
>>
>> From: eglewis71_at_gmail.com
>> To: oracle-l_at_freelists.org
>> Subject: clusterware upgrade question
>> Date: Wed, 2 Feb 2011 16:05:32 -0500
>>
>> Hi,
>> I'm getting ready to upgrade our current cluster
>> from 10.2.0.4 to 10.2.0.5 (Solaris 64-bit).
>> The components being upgraded include
>> clusterware, RAC, ASM, RDBMS , and Dataguard.
>>
>> In regard to the clusterware, we have a 2 node cluster.
>> In the patch notes, it states that all Oracle database instances
>> on all cluster nodes, must be shut down before applying the
>> clusterware patch. Later on in the notes, it states that a
>> rolling upgrade for the clusterware can be done. I'm seeing
>> conflcting messages here.
>> I've done rolling upgrades before with patch sets, but not with an
>> upgrade.
>> I've contacted Oracle support about this,but they were of little help.
>>
>> Can the clusterware upgrade be done in a rolling fashion ?
>>
>> In regard to Dataguard. We have physical standby, 2 - node cluster.
>> From what I understand, the physical standby should be upgraded before
>> the primary database (in this case a cluster). Once that is done, the
>> primary environment is then upgraded.
>> Does the primary need to be upgraded at the same time ? Can it
>> be upgraded a day or a week later ?
>>
>> thanks
>>
>> ed
>>
>
>
-- http://www.freelists.org/webpage/oracle-lReceived on Thu Feb 03 2011 - 04:57:49 CST