the CBO costs are cumulative. so in your case the total estimated cost is
24.
Kind regards,
Lex.
-----Original Message-----
From: oracle-l-bounce_at_freelists.org
[mailto:oracle-l-bounce_at_freelists.org]On Behalf Of fahd mirza
Sent: Tuesday, October 26, 2004 10:10
To: Active DBA
Subject: Optimizer Plan's Cost
Hi Listers,
I have one doubt regarding optimizer plan. would u please rectify
them.
Lets say I have a query like this
select * from foo where foo100=:b1 order by foodate;
The plan might be like this
Operation Step# Cost Select Statement 4 24 Sort (order by) 3 24 foo table access 2 22 fooidx index (range scan) 1 1
Now what would be the cost of this plan. would it be the aggregate of all
four operations that is 24+24+22+1=71 or would it be just of first operation
i.e. 24 or what? Please clarify this. thanks
regards,
Fahd
--