Home » Developer & Programmer » Data Integration » Schedule job sequentially
Schedule job sequentially [message #633277] Fri, 13 February 2015 06:50 Go to next message
alex999
Messages: 6
Registered: February 2015
Junior Member
Hello!
Im quite new into OWB. I have some jobs done and I need to schedule it sequentially. Job1 first, when Job1 is done then Job2 etc.
What is the best way to achieve something like that? Is is possible to configure it somehow or only by some scripting?

Re: Schedule job sequentially [message #633278 is a reply to message #633277] Fri, 13 February 2015 07:06 Go to previous messageGo to next message
John Watson
Messages: 8962
Registered: January 2010
Location: Global Village
Senior Member
Welcome to the forum. Please read our OraFAQ Forum Guide and How to use [code] tags and make your code easier to read

You could schedule your jobs with the Scheduler, as a job chain
http://docs.oracle.com/cd/E11882_01/server.112/e25494/schedover.htm#ADMIN12362

Before you get too deep into OWB, you might want to consider that it does not exist in the current 12.x release. So it may not have much of a future.

Re: Schedule job sequentially [message #633522 is a reply to message #633278] Fri, 20 February 2015 02:15 Go to previous messageGo to next message
alex999
Messages: 6
Registered: February 2015
Junior Member
John Watson wrote on Fri, 13 February 2015 07:06

Before you get too deep into OWB, you might want to consider that it does not exist in the current 12.x release. So it may not have much of a future.


Unfortunately we have to use OWB, client's requirement.
Re: Schedule job sequentially [message #648882 is a reply to message #633522] Sun, 06 March 2016 04:58 Go to previous message
AyushJ26
Messages: 7
Registered: March 2016
Location: Delhi
Junior Member
HI, you can put all the mappings in a script , and then schedule that script to run
Previous Topic: Script generation in OWB
Next Topic: Load Data into fact table
Goto Forum:
  


Current Time: Thu Dec 26 05:40:37 CST 2024