Copy base data [message #359520] |
Mon, 17 November 2008 01:44 |
yechiel
Messages: 7 Registered: November 2008 Location: Israel
|
Junior Member |
|
|
Is there a way to tell streams to copy the existing rows in the table when I start/define the capture process?
I want to copy a full 9i database to 10g using streams.
|
|
|
|
Re: Copy base data [message #359601 is a reply to message #359598] |
Mon, 17 November 2008 09:56 |
yechiel
Messages: 7 Registered: November 2008 Location: Israel
|
Junior Member |
|
|
I can not use export as this is a 3TB database.
I think that I saw somewhere that streams can also copy the existing data while the database is working.
This way there will be no down time.
|
|
|