Which of the following Resource Manager rules must be validated with the DBMS_RESOURCE_MANAGER.validate_pending_area procedure? (Choose three.)

A. The plan must have a directive for OTHER_GROUPS.
B . Each subplan must reference the top-level plan's consumer group.
C. Referenced subplans and/or consumer groups must exist.
D. No subplan loops.
E . The plan must have a directive for SYSTEM_GROUP.