Hi,
Scenario -
I have a discrete job demand of say Qty 15.
(ASCP Work Bench -->search with Item Name & Order Type 'Discrete Job Demand)
Post planning I can see the Supply pegged(Planned Orders) against this demand in the ASCP planner work bench (Supply/Demand Screen)
When I explode the pegging for that item , I can see that I have discrete jobs (Supply) but , they are in different planned orders.
For ex. 6 in Planned Order 1 , 6 in Planned Order 6 & 3 in Planned Order 3.
Question : Is there any way I can control the way discrete job is pegged i.e. can I make all discrete jobs fall under one planned order.
Please let me know if this is possible.