Home » RDBMS Server » Server Administration » DBMS Scheduler jobs are not running (10.2.0.4)
DBMS Scheduler jobs are not running [message #488983] Wed, 12 January 2011 11:41 Go to next message
Anand Ramaswamy
Messages: 111
Registered: January 2005
Senior Member
Hi,
I have scheduled few jobs (scheduled for each day) which has not run today, which was running successfully till yesterday. When I query dba_scheduler_jobs, i could see last_run_date as yesterday's date 6am and next_run_date is still showing today's date and time (it should show tomorrow's date/time).

Regards,
ARS
Re: DBMS Scheduler jobs are not running [message #488985 is a reply to message #488983] Wed, 12 January 2011 11:49 Go to previous messageGo to next message
John Watson
Messages: 8960
Registered: January 2010
Location: Global Village
Senior Member
HAveyou looked at the log, DBA_SCHEDULER_JOB_LOG and DBA_SCHEDULER_JOB_RUN_DETAILS ?

[Updated on: Wed, 12 January 2011 11:50]

Report message to a moderator

Re: DBMS Scheduler jobs are not running [message #488987 is a reply to message #488985] Wed, 12 January 2011 11:55 Go to previous messageGo to next message
Anand Ramaswamy
Messages: 111
Registered: January 2005
Senior Member
Hi John,
I did see these two views, it contains information for yesterday's (11-jan-2011) run and not about today's (12-Jan-2011)run.

Regds,
ARS
Re: DBMS Scheduler jobs are not running [message #490081 is a reply to message #488987] Thu, 20 January 2011 20:49 Go to previous message
ebrian
Messages: 2794
Registered: April 2006
Senior Member
As John mentioned, did you check the alert log?
Previous Topic: Oracle JOB
Next Topic: Issue in Manual DB creation
Goto Forum:
  